Federal Contractors: Recover Rising SCA Labor Costs Under Your Contract

November 18, 2026

By Peter Rauch

Federal Contractors: Recover Rising SCA Labor Costs Under Your Contract

Government contractors are no strangers to rising labor costs. Between increases to prevailing wage determinations, adjustments to fringe benefit rates, and changes in collective bargaining agreements, labor costs under Service Contract Act-covered contracts can increase significantly during contract performance.

The good news is that many contractors are entitled to recover at least some of these increased costs from the federal government. The bad news is that many fail to do so because they are unaware of the applicable contract clauses, misunderstand the scope of available relief, or fail to adequately document their increased costs.

Understanding the Service Contract Act

The McNamara-O'Hara Service Contract Act (SCA), commonly referred to in federal contracting as the Service Contract Labor Standards (SCLS), generally applies to federal service contracts exceeding $2,500 whose principal purpose is furnishing services in the United States through service employees, subject to applicable exemptions. Covered contractors and subcontractors must pay service employees at least the minimum wages and fringe benefits established by applicable Department of Labor (DOL) wage determinations or, where applicable, predecessor contractor collective bargaining agreements.

For many contractors, labor costs represent the largest component of contract performance. As wage determinations are updated and fringe benefit obligations increase, contractors may find themselves facing higher payroll expenses than anticipated when they submitted their proposal.

When Labor Costs Increase During Contract Performance

Several common events can trigger increased labor costs under an SCA-covered contract:

  • A new wage determination is incorporated at the exercise of an option year.
  • The DOL issues revised wage rates for covered labor classifications.
  • Health and welfare fringe benefit requirements increase.
  • A successor contractor becomes bound by a predecessor contractor's collective bargaining agreement.
  • Contract modifications require the incorporation of updated labor standards.

Without a mechanism for reimbursement, these increases could substantially erode profitability, particularly on long-term contracts with fixed pricing.

The Often-Overlooked Cost Recovery Clauses

Fortunately, many SCA-covered contracts contain powerful, but frequently underutilized, provisions that may allow contractors to recover increased labor costs resulting from updated wage determinations and labor standards requirements.

Most contractors are familiar with FAR 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts). As its name suggests, this clause commonly appears in fixed-price service contracts that contain option periods or otherwise extend beyond a single year. When a new wage determination or revised labor standards requirement is incorporated into the contract, FAR 52.222-43 may entitle the contractor to a price adjustment for certain increased labor costs.

Contractors should also be aware of FAR 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment, which serves a similar purpose, but it is typically used in contracts that are not subject to FAR 52.222-43, including certain contracts that do not contain option periods. Although the clauses operate somewhat differently, both are intended to prevent contractors from bearing the full financial burden of government-mandated wage and fringe benefit increases that arise during contract performance.

As a result, contractors should not assume that a fixed-price contract necessarily requires them to absorb every increase in labor costs. In many circumstances, the contract itself may provide a mechanism for recovering qualifying increases attributable to revised wage determinations, fringe benefit obligations, or collective bargaining agreement requirements.

However, contractors should not assume that every labor-cost increase is recoverable. Both clauses are generally limited to increases resulting from covered labor standards requirements and do not provide relief for ordinary market-driven wage increases, recruiting costs, retention incentives, or other business expenses unrelated to government-mandated labor standards.

What Costs Can Be Recovered?

When FAR 52.222-43 or FAR 52.222-44 applies, contractors may be entitled to a contract price adjustment for actual increases in labor costs resulting from a revised wage determination, updated fringe benefit requirement, or other covered labor standards change.

Recoverable costs may include:

  • Increased wages required by an applicable wage determination or collective bargaining agreement.
  • Increased fringe benefit obligations.
  • Additional Social Security and Medicare taxes attributable to the increased wages.
  • Additional federal and state unemployment taxes attributable to the increased wages
  • Increased workers' compensation insurance costs resulting from the required wage increases.

Importantly, FAR 52.222-43 and FAR 52.222-44 generally do not permit recovery of profit, overhead, general and administrative expenses (G&A), or other indirect costs associated with increased wages or fringe benefits.

Contractors should also understand that price adjustments are intended to compensate for actual increased costs resulting from revised labor standards requirements. Accordingly, contracting officers often require documentation demonstrating the specific labor-cost impact of a new wage determination, fringe benefit increase, or collective bargaining agreement obligation.

As a result, accurately calculating and documenting the adjustment becomes critical. Contractors that take an overly aggressive approach may face resistance from contracting officers, while those that underestimate their costs may leave money on the table.

Documentation Matters

Even where a contractor is legally entitled to an adjustment, the claim may fail if the contractor lacks supporting documentation.

Contractors should maintain records demonstrating:

  • The specific wage determination or labor standard change that caused the increase.
  • The affected employees and labor classifications.
  • The resulting increase in wages and fringe benefits.
  • Associated payroll tax impacts.
  • The methodology used to calculate the adjustment request.

Waiting until months after an option exercise or contract modification to reconstruct these figures can create unnecessary challenges and weaken an otherwise valid request.

Common Mistakes Contractors Make

Waiting Too Long to Assess Recovery Opportunities
Contractors frequently wait too long to engage with the contracting officer regarding increased labor costs. Early identification and documentation of cost impacts can help avoid disputes later in the process.

Assuming the Government Will Automatically Adjust Pricing
Price adjustments under the SCA are often not automatic. Contractors should carefully review their contract clauses and understand what steps are required to request an adjustment.

Failing to Flow Down Requirements to Subcontractors
Prime contractors can face risk when subcontractors are also subject to SCA requirements. Monitoring subcontractor compliance and obtaining timely cost information can be essential to preserving recovery opportunities.

Leaving Money Unclaimed
Some contractors focus solely on wage increases and overlook related payroll taxes and other recoverable costs. A comprehensive analysis can make a substantial difference in the final adjustment amount.

A Strategic Opportunity, Not Just a Compliance Issue

Many contractors view SCA wage increases solely as a compliance burden. In reality, these changes often present an opportunity to secure contract price adjustments that help preserve profit margins and contract performance.

As labor markets remain competitive and wage determinations continue to evolve, contractors should proactively evaluate whether recent increases may support a request for additional compensation under their federal contracts.

Takeaway

If your company performs work under an SCA-covered contract, rising labor costs do not necessarily have to come out of your bottom line. FAR 52.222-43 and FAR 52.222-44 may provide a mechanism for recovering certain increases caused by revised wage determinations, fringe benefit requirements, or collective bargaining obligations.

Contractors that view wage determination changes solely as an HR issue may be overlooking a valuable contract-management opportunity. Before accepting reduced margins as inevitable, consider a simple question: Are we recovering every dollar to which the contract entitles us?

Related People

  • Posts
  • About
  • Subscribe

Firm Highlights

  • Podcasts
    Caregiving, Community & Bradley Cooper’s Care Out Loud with Julia Wicoff
    Bradley Cooper was his father’s full-time caregiver, and that experience inspired Care Out Loud, the national caregiving campaign of his One Family Foundation. For National Family Caregivers Month, host Candace Dellacona, an advisor to Care Out Loud, talks with Julia Wicoff, the foundation’s Vice President of Partnerships and Impact. Julia is a long-distance caregiver to her parents and the legal guardian of her sister, all while raising two young daughters. She didn’t see herself as a caregiver at first, and neither do many of the 63 million Americans caring for an aging parent or a sick or disabled loved one. She explains why that label matters for getting support. She also walks through the free resources on WeCareOutLoud.org, including cheat sheets and Care Conversation Cards. And she and Candace talk about caregiving while working, how to approach HR, and how caregiver guilt and burnout show up in everyday moments. If you’re in the sandwich generation, raising kids while caring for a parent, this episode is a practical place to start. As Julia puts it: “You are a caregiver.” Chapters 0:00 For the Caregiver Who Doesn’t Know Where to Begin 1:30 How Care Out Loud Started: Bradley Cooper’s Family Foundation 3:30 A Long-Distance Caregiver’s Story 4:51 Do You Count as a Caregiver? “I’m Just Helping Out” 6:31 Why Naming Yourself a Caregiver Unlocks Support 8:18 Why Care Out Loud Sounds Like a Friend, Not a Clinic 10:51 What’s on WeCareOutLoud.org: Resources, Cheat Sheets & Conversation Cards 13:50 How to Start Hard Conversations With Aging Parents 17:51 Caregiver Feedback and Culturally Aware Cheat Sheets 19:44 Working and Caregiving: What Employees Need to Hear 22:21 Caregiving at Work: Employers, Stigma, and Culture 25:49 Policy vs. Culture: How to Ask for Flexibility at Work 30:26 Caregiver Guilt and Burnout: Freezer Aisles and Driveway Moments 33:59 How to Get Involved + Wrap Up Resources Visit Care Out Loud at https://wecareoutloud.org/ Follow Care Out Loud on Instagram: @WeCareOutLoud https://www.instagram.com/wecareoutloud/ Follow Care Out Loud on LinkedIn: https://www.linkedin.com/company/wecareoutloud/ Follow Care Out Loud on Facebook: https://www.facebook.com/wecareoutloud/ Learn more about the One Family Foundation at https://onefamilyfoundation.one/ Follow and subscribe to The Sandwich Generation Survival Guide wherever you listen to podcasts. New conversations are released on the first and third Tuesdays of every month. If this episode resonates with you, leave a five-star rating or review and share it with another sandwich generation caregiver!