Best Practices When Terminating for Cause a Downstream Contractor/Subcontractor

August 26, 2026

By Jeffrey Bright

Best Practices When Terminating for Cause a Downstream Contractor/Subcontractor

Terminating for cause a downstream contractor (or subcontractor) is considered the “nuclear option” when handling breaches of contract. Terminating for cause usually increases the risks and likelihood of litigation. Frequently, by the time the terminating party contacts the lawyer, it has already made the decision to terminate and wants the lawyer to effectuate the termination as quickly as possible. But a snap termination may cause compound problems. Instead of a quick termination, best practice is to follow a methodical, well-documented approach.

Follow the Contract Documents

Most contracts outline a process for declaring breach and terminating the contract. Generally, these steps must be followed. Some contracts identify with specific precision the types of breaches that allow for termination versus other remedies. The governing law (e.g., which state’s law applies) can have significant effect on the righteousness of a termination. Some states rigidly require all processes, notices, and terms set forth in the contract termination clauses to be satisfied prior to termination. Other states may allow exceptions to the drawn-out termination process, affording quick termination that shortcuts contractual notice clauses, depending on the circumstances. Still, whether a contract can be terminated more quickly than set forth in the contract is open to interpretation, and terminating more quickly than the contract strictly requires increases the risk of wrongful termination. Meanwhile, if the contractual processes have been followed, it significantly reduces the risk of a wrongful termination.

Thus, as a general rule of thumb, following the contract processes for declaring breach and termination is a good start.

Best Practice is to Issue a Notice to Cure

Most contracts that outline a process for termination also require issuing a notice to cure prior to termination. As previously stated, it is best to follow the contractual requirements. Even if the contract does not require a notice to cure, it is typically best practice to still issue a notice to cure.

There are two main reasons why this is recommended. First, if the default party cures the breach, then, perhaps there is no need to terminate, because the work has been brought “back on track.”  Generally, forcing the defaulting party to cure the breach at its own cost is less expensive than terminating and fronting the costs to bring in another trade to finish or cure the work.

Second, when proving that the termination was justified, typically it must be demonstrated that the defaulting party was in “material breach” of the contract. If the breach pertains to a critical component of the work, and the defaulting party fails to cure it after a proper notice, that is very strong proof that the defaulting party was in material breach and cannot perform. Thus, the termination for cause is more likely to be adjudged as righteous and justified after a failed cure opportunity. Meanwhile, if no opportunity to cure was provided, the defaulting party can argue that it would have cured the breach. If the breach could have been cured, that is strong evidence that the breach was not material (it was fixable).

Thus, a notice to cure is typically the “other foot dropping” that proves the default could not be cured and therefore the defaulting party was in material breach. Some states require a notice to cure to be issued prior to termination for cause.

Lastly, sometimes the breach has already, previously been cured by the defaulting party. Occasionally, an irritated higher-tier party will provide a lengthy list of transgressions and reasons for termination, but all of them are old, stale, and already cured. Generally, it is problematic to terminate for cause, if the reason for the termination has already been cured. Usually, terminating for cause requires the defaulting party to be in current, uncured breach at the time of termination. If terminating a party for yesteryear’s transgressions, then, you are not technically terminating for breach of contract (it was already cured); instead, you are terminating because you are still angry about it. But that is not a justified basis for termination under the law. It is an uncured (or uncurable) material breach that justifies termination, not a subjective opinion that the party was incompetent due to past issues that are of no current moment.

Document the Breach of Contract, the Remediation, and the Costs/Losses

When terminating a defaulting party, it is important to document breach. Photographs, daily logs/reports, notices to cure, and meeting minutes should corroborate and prove the breach.  Documentation of the redesign or remediation work should be well maintained, including annotated sketches or drawings to explain the details of the breach and remediation. Likewise, clear, segregated cost tracking proving the specific additional costs for remediation and cure of the issue should be maintained.

Also, best practice is to maintain documentation of the curative work to show and explain the steps taken to cure the issue. Often, the curative work itself speaks volumes as to what the problem was.

Preserve Evidence, Allow Access to Evidence, and Avoid Spoliation

Obviously, the evidence of breach, notice, termination, and the remediation work should be preserved. Relatedly, it is best to provide notice of the pending remediation work and allow the terminated party access to the site for a last inspection of the issue prior to the remediation work occurring. This is because, once the remediation work commences, the evidence of breach will inherently be destroyed and manipulated. Sometimes the terminated party will dispute the evidence, and argue that if it had been allowed the opportunity to inspect the defect, it would have been able to prove that the work was in fact satisfactory or a less expensive cure could have been utilized. The best approach is to allow the terminated party to access the site to inspect the work and observe the remediation work. The terminated party cannot interfere with the work or project, of course, but providing reasonable access for inspection (and sometimes destructive testing) is the best practice.

Lastly, sometimes, if allowed to inspect prior to the final termination, the defaulting party might present analysis or evidence to change minds about the course for remediation.

Ensure that All Interested Parties Have Been Given Notice

Sometimes there is a reason to give notice of the termination to third parties. For example, if there is a performance bond posted by the defaulting party, typically it is best to give notice to the surety. Also, sometimes the contract documents require notice of a termination to be given to either a lender, higher tier, or owner.

Consider Whether Statutes Impose a Limitation or Constraint on Termination

Sometimes the basis for termination might conflict with a separate statute. For example, under the Bankruptcy Code it is technically a violation to terminate a contract on the basis of a declared bankruptcy. You must seek bankruptcy court approval for terminating a contract with a bankrupt debtor. Other times, statutory payment acts or other statutes may require a process or steps to be taken prior to termination. This is particularly true if there are withholdings or demands for payment, which is frequently the case.

Ultimately, termination of a party on a construction project is a very strong action with significant repercussions. Missteps in the termination process can compound losses and escalate risk. Care must be taken to approach the termination with careful consideration of strategy and planning in the best interests of both the project and the litigation claims/defenses. It is highly recommended to consult with legal counsel starting with the notice and termination period. Lastly, these approaches are general points for consideration; recognize that each specific situation, project, or contract will have different factors to consider when terminating a downstream party.


JEFFREY C. BRIGHT is a Principal attorney in Offit Kurman’s Construction Practice Group and maintains a multi-state construction law practice, representing contractors, subcontractors, owners, construction managers, design-builders, and design professionals. He is licensed and active in construction law matters in PA, MD, DC, VA, and CA. In addition to handling construction litigation and project disputes, including termination of contracts mid-project, he regularly advises on the preparation, revision, and negotiation of construction contracts for various project delivery systems. He can be reached at jeff.bright@offitkurman.com.

Categories: Construction

Related People

  • Overview
  • People
  • Construction Law Blog
  • Publications & News

Firm Highlights

  • Events
    MACFO's Inside Successful CEO & CFO Partnerships
    Please join us on September 18 for an event that’s sure to be a home run! ***We will lead off by interviewing our Spotlight Speaker Series guest, Baltimore Orioles CFO, Darline Llamas Llopis.*** After, we will ask ourselves, what separates great companies from good ones? We believe that more often than not, it is the strength of the partnership between the CEO and CFO that matters, so we are bringing you three CEO/CFO leadership teams to learn from. The Associated: Jewish Federation of Baltimore – Andrew Cushnir and Sam Klein Canusa Paper & Packaging – Mike Walter and Vince Salamone Secom, LLC – Toni Toomey and Mourad Awad Join us for an exclusive executive briefing – three tandem presentations followed by a panel discussion - featuring CEOs and CFOs from different but leading organizations as they share candid insights into building trust, navigating difficult decisions, driving strategic growth, and leading through today's business challenges. You'll hear firsthand how these executive teams navigate conflict, align on priorities, and build high-performing organizations. Whether you're a CFO, controller, finance executive, or an aspiring business leader, you'll leave with practical ideas and fresh perspectives you can apply immediately. Meet Our Speakers: Darline Llamas Llopis • Orioles  Chief Financial Officer Darline Llamas Llopis is in her second season with the Orioles as Chief Financial Officer (CFO). Prior to joining the Orioles, Llamas Llopis spent four seasons with the Miami Dolphins, Hard Rock Stadium, and the F1 Miami Grand Prix as Vice President of Finance and Retail. In this capacity, she managed the finance, accounting, payroll, account payables, procurement and merchandise operations for the team and race. She also previously served for four years as the Director of Finance and Controller at the Los Angeles Rams. Llamas Llopis started her career in public accounting with Ernst & Young and PricewaterhouseCoopers as a member of the Commercial Real Estate practice.  Llamas Llopis completed her MBA at UCLA Anderson School of Management and received her Master of Accountancy from the University of Southern California (USC) where she also graduated cum laude with an undergraduate degree in business. She is a member of the American Institute of Certified Public Accountants (CPA) and is an active CPA. She resides in Baltimore with her husband, Devin, and their son, Santiago. Andrew Cushnir • The Associated: Jewish Federation of Baltimore   President & Chief Executive Officer Andrew Cushnir is the President and Chief Executive Officer of The Associated, having started in the role in May 2024. He is the eighth person to serve in this role since The Associated’s founding over 100 years ago. Andrew brings a wealth of experience and a profound dedication to strengthening and enriching the Jewish community. His journey within the Jewish Federation system began as a passionate lay leader and volunteer before he transitioned into serving as a professional. He worked for the Jewish Federation of Los Angeles for twenty years, including in the roles of Chief Planning and Program Officer and Chief Development Officer. During this time, Andrew played a crucial role in reshaping the allocation process and fostering a culture of collaboration and partnership and he also led all annual, project, and emergency fundraising, as well as planned giving efforts. As a member of the Federation’s executive team, he also addressed complex community and organizational issues. Andrew and his wife Sharon Spira-Cushnir, a seasoned nonprofit human services executive, are the proud parents of two children in their early 20s. Sam Klein • The Associated: Jewish Federation of Baltimore  Chief Financial Officer Sam Klein is a seasoned nonprofit finance executive with nearly two decades of experience leading financial strategy, operations, budgeting, and organizational transformation for mission-driven institutions. As Chief Financial Officer of The Associated: Jewish Federation of Baltimore, he oversees the organization's financial operations, investment stewardship, budgeting processes, risk management, and long-term financial planning, helping advance the Federation's mission of strengthening and supporting Jewish life in Baltimore, Israel, and around the world. Throughout his career, Sam has been recognized for his ability to align financial stewardship with organizational mission, drive process improvements, implement technology solutions, and build high-performing teams. His expertise includes nonprofit finance, strategic planning, budgeting and forecasting, investment oversight, financial reporting, compliance, operational excellence, and organizational growth. Sam earned a Master of Business Administration in Finance from the Johns Hopkins Carey Business School and a Bachelor of Science in Finance and Marketing from Syracuse University. Mike Walter • Canusa's Paper & Packaging Chief Executive Officer As Chief Executive Officer of Canusa Paper & Packaging (CPP), Mike Walter leads one of the world's leading independent international brokerages of containerboard and packaging papers. Mike recently celebrated his 20th anniversary with Canusa and has overseen a doubling of the business in the past five years. Mike’s first role at Canusa was an intern before moving into a risk management role. Progressive promotions over the years led Mike to serve as Canusa's Chief Operating Officer and General Counsel, as well as General Counsel for its affiliate, Canusa Hershman before becoming the CPP CEO on January 1st, 2025. Mike graduated with a B.S. in Commerce & Engineering from Drexel University before earning his J.D. at the University of Baltimore’s School of Law. Vince Salamone • Canusa's Paper & Packaging Chief Financial Officer Vince Salamone serves as Chief Financial Officer of Canusa Paper & Packaging, overseeing the company's global financial strategy and overall operations, risk management, and other shared services. Since joining Canusa in 2018, Vince has advanced from Corporate Controller to CFO. Prior to Canusa, Vince held senior accounting and financial reporting roles at modular space leader Algeco Scotsman and supply chain real estate operator Realterm, bringing extensive expertise in finance and corporate accounting. He began his career with Deloitte, providing assurance services to clients in aerospace and defense, software, and manufacturing throughout the Mid-Atlantic. Vince attended the University of Maryland and Towson University, earning his B.S. in Accounting in 2012 and his CPA license in 2014. Toni Toomey • Secom, LLC Chief Executive Officer As Chief Executive Officer of Secom, LLC, Toni Toomey leads the company's external vision, culture, and strategic growth. A Howard County native, Toni brings an entrepreneurial spirit and a people-first philosophy to one of Maryland's leading commercial security firms — championing internal promotion and a culture of integrity. Toni serves on the Board of Directors for Maryland Tech Council, the Howard County Chamber, as well as the Steering Committee for the Maryland Rural Tech Network. Mourad Awad • Secom, LLC Chief Financial Officer As Chief Financial Officer of Secom, LLC, Mourad Awad architects the company’s financial strategy, performance, and value creation. A leader, by example, Mourad believes in empowering people and fostering communication. With 20+ years of leadership across private equity, federal contracting, construction, and infrastructure services, Mourad brings a strategic approach to partnering with Toni – CEO to turn vision into precision execution, delivering exceptional value to Secom customers and sustainable growth for SECOM.  Thank You to Our Sponsors