Practical Steps to Take When a Schedule or Time Impact Dispute Arises

January 14, 2026

By Jeffrey Bright

Practical Steps to Take When a Schedule or Time Impact Dispute Arises

Construction projects are frequently delayed and take longer than originally anticipated. When a project is delayed, claims often arise for liquidated damages, delays, disruptions, and cost overages. Here are a few practical considerations for where to start when organizing your time impact dispute.

Start with the Schedule

Often, litigants immediately send threatening letters regarding costs, claims, losses, blame, etc.; however, it is best to start with a clear understanding of the delay as shown on the schedule. To do so, your project manager, attorney, and any expert consultant should start by reviewing key, fundamental information.

  • Was there a written contract with a completion date or milestone deadlines?
  • Were those deadlines extended by already approved change orders or extensions of time?
  • Did the contract have a baseline schedule?
  • Was the project schedule updated throughout the project?  Were there updated as-built schedules (showing the work durations, as actually performed), as well as updated projected schedules for the work yet to be completed?
  • Are the schedules available in the native software format?
  • Are there accompanying schedule narratives?

An initial analysis should start with a clear understanding of the schedule itself.

Establish why the Project was Delayed

Alongside the schedule for as-built and projected work, it is necessary to understand what events, incidents, acts, or omissions are the supposed causes of the delay. Frequently, claimants will identify a list of issues or problems on the project and assert that these caused the delays.

That’s a good start. But even better: You should be able to identify a list of time-impact events (incidents, acts, or omissions) that are the cause of the delay. And for each event, identify how and to what duration/extent it impacted the critical path of the work.

Additionally, for each event there should be proof. Text messages and emails are typically very burdensome, inefficient, and sometimes inadequate to show the event. For example, if your work is delayed because a separate trade’s predecessor work is incomplete (or incorrect), it is best to have more documentation than an email. There should be documentation showing the origin, investigation, remedial action, and conclusion of the incident. There should be photographs, daily logs, meeting minutes, RFIs, redesign, and/or change order proposals.

For each event, you should be able to present a narrative and supporting proof that concisely explains what the event was and how it impacted the critical path for the work.

Establish that Notice of the Event was Issued, and Progress it to a Formal Claim if Necessary

Typically, the contract documents differentiate notice of the event as different than a formal claim.  Notice of the event is for the purpose of addressing the issue. This serves both a legal purpose, as well as a construction purpose— to keep the project moving forward. Most contract documents will require notice to be given with reasonable promptness. This should be a documented written notice, which might accompany an RFI or other documentation, such as a change order proposal.

Recognize that notice of the issue should clarify what the issue is, and if you believe it will cause additional costs or time. If you only request additional costs or additional time, but not both, you may be waiving your right to full relief.

Generally, after the notice of the event has been issued, if the matter has not been resolved through some other means, it is best practice to issue a formal request for equitable adjustment, change order, or invoice, seeking the remedy of additional time, money, or both. It is important to track costs and delays with precision so that your requested relief is specific, reasonable, and supported by the evidence. If you fail to submit the REA/CO, then, it may be more difficult to obtain relief. Most contracts have deadlines for submitting such requests, and, further, most project players are unimpressed with end-of-project REA/CO, because it is preferred to address these issues while the item is pending and immediate.

Most contract documents will then have a “claims process” for transitioning the proposed or rejected REA/CO to a formal claim. When consulting with your attorney or expert, the quantifications (and supporting proof) for the requested time or compensation should be organized to facilitate the most efficient approach to claims handling.

To summarize:

  • Start with clear, organized documentation of the project schedule and deadlines
  • Prepare organized explanations and proof of the time impact events
  • Accurately quantify the impact with supporting proof so that the requested time and compensation are based on credible data/evidence
  • Promptly notice the time impact issue, the request for relief and, if the request is rejected, the claim

When handling time impact issues on a project, whether that be delays, disruptions, liquidated damages, or related cost overages, it is best to consult with your attorney and experts. By properly organizing, supporting, and noticing requests/claims, the preference is to reach amicable resolutions without the need for lengthy claims processes or litigation.


This article also appears in the January 2026 edition of the Spokesman, a publication of ABC Keystone.

Categories: Construction

Related People

  • Biography
  • Publications & News
  • Blog Posts
  • Featured Works

Firm Highlights

  • Events
    AIA Tri-State Conference
    Princeton will serve as the backdrop for three days of connection, learning, and design leadership. From keynotes to tours to the Tri-State Design Awards, this year’s conference is designed to go far beyond education sessions. Kick off the week with pre-conference intensives and individual state component Design Award celebrations, followed by three days of education, inspiration, networking, and design excellence at the 2026 AIA Tri-State Conference—featuring pre-conference intensives, three keynote speakers, 25 education sessions, curated tours, an expo, spec academies, and the AIA Tri-State Design Awards—bringing together architects and design professionals from New Jersey, New York, and Pennsylvania to connect, learn, and celebrate the best of the profession. G2. Designing Secure Practices: Cybersecurity, Data Privacy, Contractual Provisions, and Insurance Risks for Architects (4:00 PM - 5:30 PM) Architects and design professionals increasingly rely on cloud platforms, BIM software, and digital tools to manage sensitive data, creating cybersecurity and privacy risks. A single incident can trigger liability claims, regulatory obligations, reputational harm, and insurance challenges. Yet many firms underestimate how contracts, insurance, and internal practices intersect during a breach. This program offers legal and insurance perspectives on cyber risk in architecture, examining liability exposure, risky contract provisions, and mitigation strategies. A cyber insurance expert will explain policy responses, coverage gaps, coordination with professional liability, and best practices for aligning insurance with contractual risk and protecting firms from evolving cyber threats. Learning Objectives: Identify key cybersecurity and data privacy risks faced by architecture firms and explain how these risks can impact professional liability and project outcomes. Analyze common contractual provisions to determine which clauses may increase exposure to cyber incidents and propose strategies to mitigate these risks. Evaluate the scope and limitations of cyber insurance policies, including coordination with professional liability coverage, to determine how a policy would respond in a breach scenario. Develop actionable risk management strategies by integrating legal, contractual, and insurance considerations to protect sensitive client and project data.
  • Events
    The 2026 Economic, Tax, and Accounting Updates
    We are looking forward to the Mid-Atlantic CFO Roundtable's next event on November 13, 2026. This is a program with topics built for Finance Executives. We are extremely fortunate to have three excellent speakers: Dr. Daraius Irani, Vice President of Business and Public Engagement at Towson University; Mike Stankus, Tax Office Managing Principal at BDO; and Daniel Wahlberg, Managing Partner of Acclare Solutions. The economy is rapidly changing with various factors driving it. The November 3rd midterm elections may also have an impact. Our three expert presenters will discuss the ramifications of the election, and the current year updates to GAAP financial reporting and Federal and State income taxes. Please join us for what will surely be an informative and timely discussion. Meet Our Speakers: Daraius Irani, Ph.D. • Towson University Vice President, Business & Public Engagement Dr. Daraius Irani serves as Vice President of Business and Public Engagement at Towson University as well as the chief economist for the Regional Economic Studies Institute (RESI) at Towson University, a policy group providing economic, fiscal impact, and policy analysis to public and private entities.  Dr. Irani is often called upon to provide economic presentations to organizations across Maryland. He has appeared on numerous television programs and in local and regional print media. Dr. Irani holds a Ph.D. in economics from University of California, Santa Barbara. Dan Wahlberg • Acclare Solutions Managing Partner With over 28 years of experience, Dan Wahlberg is a recognized leader in audit and assurance for the Mid-Atlantic’s middle market business community. As a licensed CPA in Maryland and Virginia, Dan has led assurance practices at top regional firms, including serving as Baltimore Audit Managing Partner and Assurance Practice Leader at BDO USA in Baltimore and as Partner and member of the Management Committee at Hertzbach & Company P.A which merged into BDO in 2020. His expertise centers on delivering clarity, strategic guidance, and proactive solutions to middle-market businesses across Baltimore and beyond. His entrepreneurial spirit has led him to begin a new CPA firm this year with four other CPAs serving the business community. Dan holds a Bachelor of Science in Accounting from Rutgers University and began his career at PWC in New York. He is also deeply engaged in the community, previously serving as President of ACG Maryland and current Board member and as Audit Committee Member for The Associated: Jewish Federation of Baltimore.  Mike Stankus • BDO USA LLP Tax Office Managing Principal Mike Stankus is the Tax Office Managing Principal for the firm’s Baltimore office. He has more than 16 years of experience providing tax planning and preparation and management advisory services for his clients. Mike focuses on advising privately held businesses and their owners on effective growth and tax strategies. He also performs various engagements for mergers and acquisitions and complex cost accounting projects and projections. In addition, he represents various government contracting clients before the DCAA and assists with FAR compliance. Mike’s areas of concentration include working with government contractors, professional service firms, construction companies, and homebuilders.