When a problem arises on a project, it can cause significant impact to the schedule, costs, design, and sequence of work.  The problem might also require significant technical analysis to determine and ascertain the cause and best cure or remediation.  It’s therefore no surprise that contractors and subcontractors, in the midst of such situations, sometimes fail to properly focus on the contract process for formally noticing the issue and submitting it as a claim; they are too busy addressing the issue directly.  Most contract documents have specific clauses that govern the claims process, and each project might have variations to the process.  Regardless, there are certain fundamental steps that tend to be common, and all contractors and subcontractors should consider these steps when evaluating the problem because (a) your contract probably requires it, and (b) these steps tend to facilitate a proper submission, negotiation, and resolution of a claim.

Notice the Issue

The first step when encountering a problem is typically to issue a written notice of the issue.  Most contracts require notice of delays, differing site conditions, change orders, or claims within a specified period of time.  It is often confusing to initially determine if the issue is a claim or not because a claim usually indicates a dispute; meanwhile, notice of an issue could be as simple as submitting an RFI.  It depends on the circumstances.

Nevertheless, the first step is to notify the proper parties of the issue in writing.  The contract documents may require that specific issues be noticed as an RFI, change order, or request for adjustment.  The contract documents might require that the notice be submitted to the Architect of Record, owner’s representative, or a construction manager.

Typically, when initially noticing the issue, the notice will take the form directed by the contract, and it will identify the issue at hand, with any supporting documentation to explain or present the issue. It should also identify whether additional time or costs are likely to result from the issue.

Transitioning the Notice of an Issue to a Formal Claim

Often, a problem on a project will start with notice of the issue, and it will progress and develop into a claim.  For example, a sinkhole on a project will typically result first in an RFI, project meeting minute, or change order proposal that identifies the sinkhole and declares it to be a differing site condition or issue needing the attention of the owner or Architect of Record.  Thus, the first discussion of the item is typically a notice, not a formal claim.

Typically, in response to the notice of the issue, instruction or direction will be provided by the owner or Architect of Record on the work to be performed.  The instruction might be in the form of a change order, change directive, or a response to an RFI.  If the directed action is agreeable and provides an acceptable adjustment to the time or price for the work, then the issue is often resolved through this natural course of conduct.

But if the parties disagree on the direction, lack of direction, or the proposed compensation or extension of time, then the matter has developed into a claim/dispute.  The cautious and prudent contractor recognizes that if it fails to lodge and preserve its disagreement and instead simply signs a change order, it could potentially waive its rights to additional time or compensation, depending on the circumstances.

Typically, the contract documents will provide a specific process for progressing the claim, and the first step of the claim process is to submit a written claim within a specified time period.  Thus, in the hypothetical example at hand, once the issue has been noticed and developed into a disagreement, that is when the notice of claim should be submitted.  I often see contractors that initially notice the issue but then fail to submit a formal claim once the issue has reached an impasse.

The submission of the claim might be rather simple, or it might be complex.  For example, the AIA A201 requires that claims be submitted to the “Initial Decision Maker,” who is typically the Architect of Record.  The Architect of Record then responds to the noticed formal claim, and if the matter is still in dispute, the claim proceeds to either mediation, arbitration, or litigation.

Some contracts have very extensive and complicated processes for submitting the claim, which require specific information or supporting documentation.  And some contracts have extensive processes where the initial decisions on the claim, either from the owner or Architect of Record, may take several steps with decisions rendered at each step.

It is important to properly present the claims to the correct persons, with the correct information, and if the claim is denied to promptly notice the appeal of the decision in conformance with the contract.

Proper notice and submission of a claim is important because a failure to do so may result in a waiver of the claim.  Thus, it is important to issue both a written formal notice of the issue and an additional notice of claim when the issue has not been resolved to satisfaction.  Additionally, a properly developed and presented claim—containing supporting documentation and clear explanation of the issues with legal and expert analysis if necessary—is in a significantly better position for negotiated resolution.  The best practice is to consult with trusted, experienced counsel that is knowledgeable on the intricacies of construction law. Offit Kurman construction attorneys are available to advise and counsel contractors, construction managers, design-builders, design professionals, subcontractors, and developers on construction contracts, risk, and project disputes.

Categories: Construction

Related People

  • Overview
  • People
  • Construction Law Blog
  • Publications & News

Firm Highlights

  • Events
    AIA Tri-State Conference
    Princeton will serve as the backdrop for three days of connection, learning, and design leadership. From keynotes to tours to the Tri-State Design Awards, this year’s conference is designed to go far beyond education sessions. Kick off the week with pre-conference intensives and individual state component Design Award celebrations, followed by three days of education, inspiration, networking, and design excellence at the 2026 AIA Tri-State Conference—featuring pre-conference intensives, three keynote speakers, 25 education sessions, curated tours, an expo, spec academies, and the AIA Tri-State Design Awards—bringing together architects and design professionals from New Jersey, New York, and Pennsylvania to connect, learn, and celebrate the best of the profession. G2. Designing Secure Practices: Cybersecurity, Data Privacy, Contractual Provisions, and Insurance Risks for Architects (4:00 PM - 5:30 PM) Architects and design professionals increasingly rely on cloud platforms, BIM software, and digital tools to manage sensitive data, creating cybersecurity and privacy risks. A single incident can trigger liability claims, regulatory obligations, reputational harm, and insurance challenges. Yet many firms underestimate how contracts, insurance, and internal practices intersect during a breach. This program offers legal and insurance perspectives on cyber risk in architecture, examining liability exposure, risky contract provisions, and mitigation strategies. A cyber insurance expert will explain policy responses, coverage gaps, coordination with professional liability, and best practices for aligning insurance with contractual risk and protecting firms from evolving cyber threats. Learning Objectives: Identify key cybersecurity and data privacy risks faced by architecture firms and explain how these risks can impact professional liability and project outcomes. Analyze common contractual provisions to determine which clauses may increase exposure to cyber incidents and propose strategies to mitigate these risks. Evaluate the scope and limitations of cyber insurance policies, including coordination with professional liability coverage, to determine how a policy would respond in a breach scenario. Develop actionable risk management strategies by integrating legal, contractual, and insurance considerations to protect sensitive client and project data.
  • Events
    The 2026 Economic, Tax, and Accounting Updates
    We are looking forward to the Mid-Atlantic CFO Roundtable's next event on November 13, 2026. This is a program with topics built for Finance Executives. We are extremely fortunate to have three excellent speakers: Dr. Daraius Irani, Vice President of Business and Public Engagement at Towson University; Mike Stankus, Tax Office Managing Principal at BDO; and Daniel Wahlberg, Managing Partner of Acclare Solutions. The economy is rapidly changing with various factors driving it. The November 3rd midterm elections may also have an impact. Our three expert presenters will discuss the ramifications of the election, and the current year updates to GAAP financial reporting and Federal and State income taxes. Please join us for what will surely be an informative and timely discussion. Meet Our Speakers: Daraius Irani, Ph.D. • Towson University Vice President, Business & Public Engagement Dr. Daraius Irani serves as Vice President of Business and Public Engagement at Towson University as well as the chief economist for the Regional Economic Studies Institute (RESI) at Towson University, a policy group providing economic, fiscal impact, and policy analysis to public and private entities.  Dr. Irani is often called upon to provide economic presentations to organizations across Maryland. He has appeared on numerous television programs and in local and regional print media. Dr. Irani holds a Ph.D. in economics from University of California, Santa Barbara. Dan Wahlberg • Acclare Solutions Managing Partner With over 28 years of experience, Dan Wahlberg is a recognized leader in audit and assurance for the Mid-Atlantic’s middle market business community. As a licensed CPA in Maryland and Virginia, Dan has led assurance practices at top regional firms, including serving as Baltimore Audit Managing Partner and Assurance Practice Leader at BDO USA in Baltimore and as Partner and member of the Management Committee at Hertzbach & Company P.A which merged into BDO in 2020. His expertise centers on delivering clarity, strategic guidance, and proactive solutions to middle-market businesses across Baltimore and beyond. His entrepreneurial spirit has led him to begin a new CPA firm this year with four other CPAs serving the business community. Dan holds a Bachelor of Science in Accounting from Rutgers University and began his career at PWC in New York. He is also deeply engaged in the community, previously serving as President of ACG Maryland and current Board member and as Audit Committee Member for The Associated: Jewish Federation of Baltimore.  Mike Stankus • BDO USA LLP Tax Office Managing Principal Mike Stankus is the Tax Office Managing Principal for the firm’s Baltimore office. He has more than 16 years of experience providing tax planning and preparation and management advisory services for his clients. Mike focuses on advising privately held businesses and their owners on effective growth and tax strategies. He also performs various engagements for mergers and acquisitions and complex cost accounting projects and projections. In addition, he represents various government contracting clients before the DCAA and assists with FAR compliance. Mike’s areas of concentration include working with government contractors, professional service firms, construction companies, and homebuilders.